Texas Regulators Resume Issuing Air Permits for Data Centers

Data center permitting had been placed on hold while an audit took place.

Data center

Texas regulators began issuing air permits for data centers again after receiving notice that the state’s electric grid operator had finished gathering information on the projects’ potential impacts.

“The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations,” Texas Commission on Environmental Quality spokesperson Laura Lopez wrote in a statement.

In August, Gov. Greg Abbott directed the Public Utility Commission of Texas and the Electric Reliability Council of Texas to audit data center projects seeking to connect to the grid and pause their progress through the connection process.

At the time, the Electric Reliability Council of Texas was considering 474 gigawatts of requests to connect to the grid, with Abbott’s office stating that about 90 percent of that came from data centers.

In September, Abbott halted all permitting for data centers while the audit continued. He said that that data center project developers should cover electrical infrastructure costs, report electricity and water usage, and avoid using water needed by local communities.

Abbott previously announced plans to work with lawmakers during the next legislative session to eliminate financial incentives for data centers.

However, Abbott will be replaced by Democrat Gov.-elect Gina Hinojosa in January.